Wind Turbine Complaint Investigation

Compliance investigation of a large turbine site which required the deployment of 6 noise meters around the site with comprehensive analysis and recording capabilities.

The data from the noise campaign demonstrated that the windfarm was operating in compliance with planning permission provided that minor constaints on the turbine operations was implemented.

Long-term monitoring to inform constraint programme following noise complaints

Wind Turbine Complaint Investigation